  2. OFBIZ-7111

Total Actual cost of production run need to be passed on to produced stock's unit cost for completed production run

    XMLWordPrintableJSON

Details

    • New Feature
    • Status: Reopened
    • Major
    • Resolution: Unresolved
    • Release Branch 14.12, 14.12.01, Release Branch 15.12, 15.12.01
    • None
    • manufacturing
    • None

    Description

      Currently as soon as item is produced into inventory once production run is completed then inventory get created with ZERO unit cost.

      We could pass on the total actual cost (Material+Labor+Resource etc.) to Produced Item's inventory item i.e. = Total Actual Cost/ Produced in Stock

      Please refer to attached screenshot for reference

      Attachments

        1. ActualCostXfer_2.png
          135 kB
          Swapnil Shah
        2. ActualCostXfer_1.png
          111 kB
          Swapnil Shah
        3. OFBIZ-7111.patch
          2 kB
          Anuj Jain
        4. OFBIZ-7111_V2.patch
          2 kB
          Ankush Upadhyay
        5. OFBIZ_7111.png
          77 kB
          Swapnil Shah

        Activity

          People

            anuj.jain Anuj Jain
            swash78 Swapnil Shah
            Votes:
            0 Vote for this issue
            Watchers:
            5 Start watching this issue

            Dates

              Created:
              Updated: