Project resource overview doesn't show the resources with a thru-date before the current date.

    Details

    • Type: Bug Bug
    • Status: Closed
    • Priority: Major Major
    • Resolution: Fixed
    • Affects Version/s: Release 10.04, Release Branch 11.04, SVN trunk, Release 11.04.01
    • Fix Version/s: SVN trunk
    • Labels:
      None

      Description

      When a project manager expires the assignment of a resource by clicking the delete button in the Project Resources overview the resource is deleted from the overview. It should be that the resource is still shown in the overview with the tru-date visible.

      Otherwise there will be a discrepancy between the overview of resources of the project and the project dashboard.

      The name of the button is also wrong. It should state 'expire' not 'delete'.

        Activity

        Hide
        Jacques Le Roux added a comment -

        Thanks Pierre,

        Your patch is in trunk at r1338695. Only in trunk because this was not a bug but an improvement.

        As you suggested, I have also created and used a new label FormFieldTitle_expireButton copying labels from CommonExpire.

        Show
        Jacques Le Roux added a comment - Thanks Pierre, Your patch is in trunk at r1338695. Only in trunk because this was not a bug but an improvement. As you suggested, I have also created and used a new label FormFieldTitle_expireButton copying labels from CommonExpire.
        Hide
        Pierre Smits added a comment -

        This patch fixes the bug.

        Show
        Pierre Smits added a comment - This patch fixes the bug.

          People

          • Assignee:
            Jacques Le Roux
            Reporter:
            Pierre Smits
          • Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

            • Created:
              Updated:
              Resolved:

              Time Tracking

              Estimated:
              Original Estimate - 0.5h
              0.5h
              Remaining:
              Remaining Estimate - 0.5h
              0.5h
              Logged:
              Time Spent - Not Specified
              Not Specified

                Development