    Description

      There were a bunch of problems (also copied below) with clock getting stuck after call to update() until it's own system time caught up.


      PT = physical time, LT = logical time, ST = system time, X = don't care terms


      Core issue:

      • Note that in current implementation, we are passing master clock to RS in open/close region request and RS clock to master in the responses. And they both update their own time on receiving these request/response.
      • On receiving a clock ahead of its own, they update their own clock to its PT+LT, and keep increasing LT till their own ST catches that PT.

      Proposed solution:
      Keep track of skew in clock. And instead of keeping track of physical time, always compute it by adding system time and skew.
      On update(), recalculate skew and validate if it's greater than max_skew.
      On toTimestamp(), calculate PT = ST+skew.



      Issues with current approach:


      Problem 1: Logical time window too small.
      RS clock (10, X)
      Master clock (20, X)
      Master -request> RS
      RS clock (20, X)
      While RS's physical java clock (which is backing up physical component of hlc clock) will still take 10 sec to catch up, we'll keep incrementing logical component. That means, in worst case, our logical clock window should be big enough to support all the events that can happen in max skew time.
      The problem is, that doesn't seem to be the case. Our logical window is 1M events (20bits) and max skew time is 30 sec, that results in 33k max write qps, which is quite low. We can easily see 150k update qps per beefy server with 1k values.
      Even 22 bits won't be enough. We'll need minimum of 23 bits and 20 sec max skew time to support ~420k max events per second in worst case clock skew.


      Problem 2: Cascading logical time increment.
      When more RS are involved say - 3 RS and 1 master. Let's say max skew is 30 sec.
      HLC Clocks (physical time, logical time): X = don't care
      RS1: (50, 100k)
      Master: (40, X)
      RS2: (30, X)
      RS3: (20, X)
      [RS3's ST behind RS1's by 30 sec.]
      RS1 replies to master, sends it's clock (50,X).
      Master's clock (50, X). It'll be another 10 sec before it's own physical clock reaches 50, so HLC's PT will remain 50 for next 10 sec.
      Master --> RS2
      RS2's clock = (50, X).
      RS2 keeps incrementing LT on writes (since it's own PT is behind) for few seconds before it replies back to master with (50, X+ few 100k).
      Master's clock = (50, X+ few 100k) [Since master's physical clock hasn't caught up yet, note that it was 10 seconds behind, PT remains 50.].
      Master --> RS3
      RS3's clock (50, X+few 100k)
      But RS3's ST is behind RS1's ST by 30 sec, which means it'll keep incrementing LT for next 30 sec (unless it gets a newer clock from master).
      But the problem is, RS3 has much smaller LT window than actual 1M!!

      Problem 3: Single bad RS clock crashing the cluster:
      If a single RS's clock is bad and a bit faster, it'll catch time and keep pulling master's PT with it. If 'real time' is say 20, max skew time is 10, and bad RS is at time 29.9, it'll pull master to 29.9 (via next response), and then any RS less than 19.9, i.e. just 0.1 sec away from real time will die due to higher than max skew.
      This can bring whole clusters down!

      Problem 4: Time jumps (not a bug, but more of a nuisance)
      Say a RS is behind master by 20 sec. On each communication from master, RS will update its own PT to master's PT, and it'll remain that till RS's ST catches up. If there are frequent communication from master, ST might never catch up and RS's PT will actually look like discrete time jumps rather than continuous time.
      For eg. If master communicated with RS at times 30, 40, 50 (RSs corresponding times are 10, 20, 30), than all events on RS between time [10, 50] will be timestamped with either 30, 40 or 50.

      Attachments

        1. HBASE-18432.HBASE-14070.HLC.001.patch
          31 kB
          Apekshit Sharma
        2. HBASE-18432.HBASE-14070.HLC.002.patch
          9 kB
          Apekshit Sharma

        Issue Links

          Activity

            People

              Unassigned Unassigned
              appy Apekshit Sharma
              Votes:
              0 Vote for this issue
              Watchers:
              3 Start watching this issue

              Dates

                Created:
                Updated: