      Steps to reproduce: 

      1. Dusburse a loan of a dynamic loan product
      2. make a repayment in between two instalments
      3. compare the transaction and the schedule

      Actual result:

      The schedule shows that the paid amount reduces the principal, and interest is calculated accordingly which remains outstanding. The transaction amount is allocated differently though, it shows that the interest is paid and only the remaining amount is spent on the principal. 

      Schedule: 

      Transaction:

      Expected result:

      The payment is spent on the interest until payment date. The remaining spent on the balance and interest due is calculated for the rest of the days till next installment due.

      Attachments

        1. image-2024-10-18-10-06-00-062.png
          47 kB
          Mihaly Dallos
        2. image-2024-10-18-10-14-41-963.png
          35 kB
          Mihaly Dallos
        3. image-2024-10-18-10-19-50-306.png
          48 kB
          Mihaly Dallos

        Activity

          People

            Unassigned Unassigned
            mdallos Mihaly Dallos
            Votes:
            0 Vote for this issue
            Watchers:
            0 Start watching this issue

            Dates

              Created:
              Updated: