    Description

      GIVEN The business date is not enabled
      WHEN Increase business date by 1 day job got executed
      THEN so the business date will not be increased, but at the end it shows, it was executed successfully.

      Should we mark it as SKIPPED!

      Reproduce

      • Enable the job
      • Disable business date in config

       

       

      Acceptance criteria

      • We should mark this job as SKIPPED, if the business date is not enabled
      • Both Business date and COB date job to be updated