      In the scheduling loop, if the number of ackers to be scheduled along with the executor is greater than zero, and they cannot all fit, then try to fit as many ackers as possible.

      To do this, fit the executor first. If this succeeds, then attempt to fit as many ackers are possible upto and including the max required as per calculation (and as low as zero). This second step should not fail.

      Attachments

        Issue Links

          Activity

            People

              bipinprasad Bipin Prasad
              bipinprasad Bipin Prasad
              Votes:
              0 Vote for this issue
              Watchers:
              2 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved:

                Time Tracking

                  Estimated:
                  Original Estimate - Not Specified
                  Not Specified
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 20m
                  20m