Index: site-author/incubation/Process_Description.xml =================================================================== --- site-author/incubation/Process_Description.xml (revision 704289) +++ site-author/incubation/Process_Description.xml (working copy) @@ -26,6 +26,17 @@
++ This document is an overview of the process. Read it in conjunction with + the "Incubation Policy" and the + various guides. + Also review the + Roles and Responsibilities + for a description of the various parties involved in the Incubation process. +
+
Readers should also review the - - Roles and Responsibilities -document for a description of the various parties involved in the -Incubation process. - -
If that vote is affirmative, the Sponsor will propose to the +
If that vote is affirmative, the Sponsor (unless the Sponsor is already the Incubator PMC) + will propose to the Incubator PMC (referencing the voting result e-mail) that your candidate project be Index: site-author/incubation/Incubation_Policy.xml =================================================================== --- site-author/incubation/Incubation_Policy.xml (revision 704289) +++ site-author/incubation/Incubation_Policy.xml (working copy) @@ -235,8 +235,15 @@
Upon a successful result, the PMC Chair of the Sponsor SHOULD request the Incubator -PMC take on the Candidate as a new Podling. The request, +
Upon a successful result, the PMC Chair of the Sponsor SHOULD request that the Incubator +PMC take on the Candidate as a new Podling.
++ However when the Sponsor is the Incubator PMC, then they were the group of people + who just voted. So the normal vote summary is sufficient. +
++ Otherwise the Sponsor is an existing top-level project PMC, which now needs + to notify the Incubator PMC. The request, which should be sent to the Incubator PMC on the general list, MUST contain the following information: @@ -260,11 +267,14 @@ If any Incubator PMC member says "hold" before the 72 hours are up, a formal discussion/vote will be conducted.
+The nominated Mentors MAY be immediately accepted by the Incubator PMC. However the Incubator PMC MAY also suggest replacement Mentors. The Incubator PMC has the final choice of Mentors.
+