Currently any new product added against given routing task via Actual Material screen just reflects the inventory statistics it.
We could try to add the feature of having the added products actually be added in conjunction with Actual projected Material requirement based on original BoM associated with the routing.
- This could be done by creating fresh WorkEffortGoodStandard (WEGS) with such added products against specified routing.
- We can begin with simple constraint of allowing new material against the only those routing task that has not cancelled yet within a production run
- Any completed taks should have WEGS created in COMPLETED status and WEIA created as well by issuing the added item's qty.
- Start showing such newly added material requirement in conjunction with original requirement (based on BoM) under all relevant sections over Production Declaration Screen
Please refer to attached screenshot for reference
Attachments
Attachments
Issue Links
- relates to
-
OFBIZ-7468 Define constraints while adding new material to the task which is in completed/cancel status.
- Reopened
-
OFBIZ-7454 [OFBIZ-7173] Any new product added against given routing task via Actual Material screen is not reflected on production run declaration screen.
- Closed
-
OFBIZ-7485 Documentation: Unit Test (Use)Cases for OFBIZ-7173
- Closed