Details
-
Bug
-
Status: Closed
-
Major
-
Resolution: Fixed
-
Release Branch 09.04
-
None
Description
Not possible to add resource to task in the project manager application
Try the following:
1. Enter the project manager application
2. Select Project in at the menu
3. Select the project "Demo Project1 Cust1[9000]"
4. Select task3 in the task-overview-window
5. Select Resources
6. Select "Analist1 Jo" add the date and press "Add"
----------
The Result:
-----------
The following message is shown:
–
The Following Errors Occurred:
In set-nonpk-fields a value was not found with the specified valueAcsr: assignment, not setting fields
—
-----------------
Work-around
------------------
Logg in as Analist1, and assign the task. That will work.