    Description

      This is the task of releasing Apache (incubation) NetBeans 10

      Attachments

        Issue Links

          1.
          Check the Blocker issues Sub-task Closed Laszlo Kishalmi  
          2.
          Check the Critical issues Sub-task Closed Unassigned  
          3.
          Check the pull issues with pull requests. Sub-task Closed Laszlo Kishalmi  
          4.
          Check the open PR list on GitHub Sub-task Closed Laszlo Kishalmi  
          5.
          Branch master to release10 Sub-task Closed Laszlo Kishalmi  
          6.
          Re-Configure the Release job on Jenkins Sub-task Closed Laszlo Kishalmi  
          7.
          Update currentVersion to Show 10.0 as version number. Sub-task Closed Unassigned  
          8.
          Update JavaDoc Generation Sub-task Closed Unassigned  
          9.
          Create first vote candidate Sub-task Closed Laszlo Kishalmi  
          10.
          Change the launcher settings for release Sub-task Closed Unassigned  
          11.
          Adjust Update Centers Sub-task Closed Unassigned  
          12.
          Increment Spec Versions on Release Branch Sub-task Closed Unassigned  
          13.
          Increment Spec Versions on Master Baranch Sub-task Closed Unassigned  
          14.
          Update pluginimporter and upgrader tool to look for NetBeans 9.0 Sub-task Closed Unassigned

          100%

          Original Estimate - Not Specified Original Estimate - Not Specified
          Time Spent - 0.5h
          15.
          Update the Snap package descriptor files Sub-task Closed Laszlo Kishalmi

          100%

          Original Estimate - Not Specified Original Estimate - Not Specified
          Time Spent - 1h 10m
          16.
          Create a Location for NB 10 Standard Distribution AUC Sub-task Closed Laszlo Kishalmi  
          17.
          Create 2nd Vote Candidate Sub-task Closed Laszlo Kishalmi  
          18.
          UpgradeWindows Launchers Sub-task Closed Jan Lahoda

          100%

          Original Estimate - Not Specified Original Estimate - Not Specified
          Time Spent - 1h
          19.
          Create 3rd Vote Candidate Sub-task Closed Laszlo Kishalmi  
          20.
          Collect Vote Results on VC3 Sub-task Closed Laszlo Kishalmi  
          21.
          Create IPMC Vote Thread Sub-task Closed Laszlo Kishalmi  
          22.
          Close IPMC Vote Thread Sub-task Closed Laszlo Kishalmi  
          23.
          Copy staged release artifacts to the release area. Sub-task Closed Laszlo Kishalmi  
          24.
          Update the WebSite for the new Release Sub-task Closed Laszlo Kishalmi  
          25.
          Send out release announcement-s Sub-task Closed Laszlo Kishalmi  
          26.
          Archive the old 9.0 release artifacts. Sub-task Closed Laszlo Kishalmi  
          27.
          Update Release Management Wiki Sub-task Closed Laszlo Kishalmi  
          28.
          Snapshot of APIs as of release 10.0 Sub-task Closed Jaroslav Tulach  

          Activity

            People

              lkishalmi Laszlo Kishalmi
              lkishalmi Laszlo Kishalmi
              Votes:
              0 Vote for this issue
              Watchers:
              10 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved:

                Time Tracking

                  Estimated:
                  Original Estimate - Not Specified
                  Not Specified
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 2h 40m
                  2h 40m