Gobblin will skip all future tasks if the first n tasks complete before the n+1th is scheduled

    XMLWordPrintableJSON

Details

    • Bug
    • Status: Resolved
    • Major
    • Resolution: Fixed
    • None
    • 0.13.0
    • None
    • None

    Description

      Issue with `CountUpAndDownLatch` where the latch will complete if at any point all tasks are completed, ignoring any future countUps.